Biogeneration Stack Rehabilitation

As the lead contractor on the project GRA was able to efficiently manage inspection and welding repairs in the vent stacks of a large power facility. The repairs required a shutdown of the facility so time was of the essence. Using rope access we were able to complete the required welding repairs and inspection in less time, and at a reduced cost.

Work Site

  • 200m tall Corten Steel Stack

Scope

Rigging and Rope Access
Visual Inspections
Magnetic Particle Inspections
Welding Deficiencies
Confined Space Program
Confined Space Hazard Assessment (CSHA) completed by GRA Industrial Hygienist
Project Management, Safety & Rescue Plans